Rigging & cranes
Register slings and cranes and record frequent and periodic inspections that remove a failed unit from service; overdue inspections escalate, and registers can be bulk-imported from a spreadsheet.
This module tracks rigging and lifting equipment under OSHA 1910.179(j) (overhead cranes) and 1910.184(d)/(e) (slings) — a frequent inspection and a periodic (annual) inspection per unit. The frequent cadence follows the equipment type: before-use (daily) for slings and below-the-hook devices, monthly for overhead cranes and hoists. A failed inspection removes the unit from service.
Register equipment
- Under Register equipment, choose the site and enter the asset tag and description.
- Pick the type (chain sling, wire-rope sling, crane, and so on) and the working load limit (WLL) in pounds.
- Click Register. The unit joins the list with its frequent and periodic due dates.
Record an inspection
- Filter by Site if needed, then find the unit in the list.
- Click Frequent ✓ or Periodic ✓ to pass that inspection — the matching due date rolls forward.
- Click Fail/RFS to remove a unit from service; when repaired, click Return to put it back.
Follow up
- An overdue date shows in bold red, and the row turns yellow (an inspection has lapsed) or red (removed from service).
- For a unit needing attention, click CAPA to open a corrective action; the row then links to that CAPA.
- Decommission permanently retires scrapped gear — it drops out of every attention count, but its history stays on record.
- Export register CSV downloads the rigging register — inspection dates, service status, and
recorded defects — from
api/rigging/register.csv.
Import your register
Bring an existing equipment list in through spreadsheet import: the Rigging & lifting equipment target accepts SiteId (your site's name works — no codes needed), AssetTag, Description, RiggingType, RatedCapacityLb, and InServiceOn columns, and the downloadable sample workbook includes a ready-made sheet.
Mobile cranes (OSHA 1926 Subpart CC)
Below the 1910 slings/overhead-crane register is a second, distinct register for mobile cranes under 1926 Subpart CC (cranes & derricks in construction). It has its own inspection cadence and site controls — it is not the same list as the 1910 rigging above.
- Under Register a mobile crane, choose the site and enter the asset tag, description, type, and capacity (t) in tons, then click Register crane. Cranes are UI-registered only — there is no spreadsheet import for them (unlike the 1910 rigging register).
- Cranes run a dual cadence: click Monthly ✓ (30-day documented inspection) and Annual ✓ (365-day comprehensive inspection, 1926.1412) on their own clocks. Fail/RFS removes the crane from service; Return restores it.
- Click Edit to open the operator & site-conditions panel:
- Operator certification (1926.1427) — pick the certified operator, enter a certification reference (e.g. NCCCO #), and tick Certification current, then Record operator.
- Site conditions — tick Power-line hazard assessed (1926.1408) and Ground conditions assessed (1926.1402) with notes, and name the A/D director (1926.1403-04), then Save conditions.
- A crane reads unsafe to operate (red row) when any one of these is true: it is removed from service, has no certified operator, or its power-line hazard is not assessed.
- Export crane register CSV downloads the crane register with inspection dates, operator cert,
and site controls (
api/rigging/cranes/register.csv).
What happens automatically
- When an inspection lapses on an in-service unit, the escalation sweep raises an overdue notification addressed to the Safety Team for that site, with a link back to this page. An overdue periodic (annual) inspection is reported first; otherwise the overdue frequent one. Set who's emailed for that queue under notification routing.
- Every unit removed from service after a failed inspection also escalates — "Rigging removed from service: (asset tag)" — and stays escalated until it's repaired/destroyed or returned to service, since defective rigging within reach is one improvised lift from a dropped load.
- A mobile crane that is unsafe to operate escalates as a danger — "Mobile crane unsafe to operate: (asset tag)" — with the reasons (removed from service, no certified operator, or power-line not assessed); otherwise an overdue annual or monthly inspection escalates.
- Repeated sweeps don't pile up duplicate notifications for the same condition.
Tip: frequent and periodic are two separate clocks — record each on its own button so a current frequent check never hides an overdue annual one.
Related
- Permits to work — Authorize higher-risk critical lifts
- CAPA (corrective & preventive actions) — Correct failed-inspection findings to closure
- Asset safety passports — QR passport showing live equipment safety state